Mac Mine Worker Village

March 2011 - July 2011

Client Information

The Mac Group

  • Duration: 16 weeks
  • Value: $1.4 million
  • Location: Narrabri, North West NSW
  • Project Details

Scope of Work

The Mac Mine Worker Village project included the civil works associated with the construction of the first stage of a mine worker village at Narrabri.  Work commenced in December 2010 and was completed in March 2011.

Significant Achievements

  • Work completed within client required timeframes despite wet weather
  • Over 800t asphalt wearing course
  • Surface and subsurface drainage works
  • 1.5km kerb and gutter
  • Bulk earthworks and village building pads
  • Use of laser buckets, ATS and GPS controlled plant
  • 12,000t pavement
  • 10ML detention basin and drainage blanket
  • Concrete works including multi-cell cast in-situ headwalls, wingwalls, encasement slabs and aprons.