Client Information

Client:
AGL Macquarie
Duration:
January 2021 — September 2021
Value:
$1.5M
Location:
Ravensworth, NSW
Contact Us

Summary

The AGL Void 5 Project included the construction of multiple earthen dam walls comprising 130,000m3 of selected fill material. These earthen dam walls were constructed at the Ravensworth Void 5 North and South Arm Locations. This allowed for the continued depositing of fly ash in the void 5 location.

  • Below is a summary of constructed walls and respective volumes completed as part of this project;
  • Construction of 1B Bund Wall (16,000m3);
  • Construction of 5N Bund Wall (18,000m3);
  • Construction of Seal Wall between Bunds 1B and 5N (37,000m3);
  • Construction of North Arm Bund 4L (45,000m3); and
  • Construction of North Arm Seal Wall (15,000m3).

Scope of work

The AGL Void 5 Project scope included:

  • Site mobilisation, inductions, preliminaries and planning;
  • Establishment of access tracks and construction ramps;
  • Clearing and establishment of works area;
  • Excavation of “key” in deposited ash material;
  • Construction of bridging layers over deposited ash material;
  • Construction of multiple dam walls in accordance with specifications;
  • Winning, sorting material from the allocated borrow pit, ensuring it conforms to material requirements;
  • Placement, conditioning, compaction and trimming of earthworks;
  • Environmental management; and
  • All supervision and construction management.

Achievements

  • Managing operational challenges of working in old mine work
  • areas and over deposited fly ash material;
  • Working within limited operational working area using a large fleet of civil earthmoving equipment;
  • Wining and sorting suitable fill material to meet dam wall specification requirements; and
  • Environmental management of operational fleet over large area.