Client Information
Summary
ARTC’s FY20 Annual Works Plan (AWP) includes a structures component within the Hunter Valley Rail Corridor. Part of this work is for the replacement of the following bridges within the Hunter Valley network:
- Merrygoen 408.791km
- Premer 530.997km
- Premer 531.466km
- Premer 532.250km
Scope of Works
- Precast and cast insitu concrete works;
- Supply and haulage of all precast elements for the works;
- Track removal and replacement;
- Regrading of drainage lines and installation of scour protection;
- Demolition and replacement of existing timber bridge structure at Merrygoen approximately 20m long and 4.5m high;
- Demolition and replacement of three existing timber bridge structures at Premer approx. 55m long and 1.5m high;
- Install of culverts at Merrygoen, approximately 42t each; and
- Install of culverts at Premer, approximately 18t each.
Achievements
- Successfully managing the delay on the Premer project due to flooding immediately prior to the scheduled possession;
- Successfully managing the rescheduling of the Merrygoen project due to COVID-19 restrictions; and
- Working around the wet and soft ground conditions at Merrygoen requiring a last minute change to the foundation design prior to the works and diversion of ongoing creek flows during installation.