December 2016 - May 2017

Client Information

ARTC

  • Duration: December 2016 - May 2017
  • Value: $700,000
  • Location: Colley Creek, NSW

Scope of Work

  • Replacement of a life expired transom bridge with a ballast top concrete culvert bridge
  • Works included supply of all precast elements which was undertaken internally by Daracon
  • All removal and installation works delivered in the 72hr February 2017 possession
  • All works including precast and insitu concrete, earthworks, track work and heavy transport completed by Daracon resources
  • Heavy lifting completed using a 300T crane for the 23T lift at 26m radius

Significant Achievements

  • Self delivery of all major project items
  • Works completed on time during the possession window
  • Precast products of a high standard and exceeded ARTC expectations